Construction Change Directive (CCD)
Free to fill in and print in your browser. A printable, owner-directed change when agreement on cost or time has not been reached — directs work to proceed while negotiations continue. Auto-calculating cost estimate with markup. Edit inline, print clean. Need to save your data, add your logo, or reuse across projects? Get the template pack ↓
- Save data · reuse across projects
- Add your logo & company branding
- Works offline · no login
Project & Parties
Basis of Directive
Scope of Directed Work
Preliminary Cost Estimate
| Cost Category | Estimated Amount | Notes |
|---|---|---|
| Estimated Total | $0 |
Method of Determining Final Cost
Schedule Impact
Contractor Obligations
- The Contractor shall proceed with the directed work immediately upon receipt of this directive, regardless of whether agreement has been reached on cost or time.
- The Contractor shall maintain detailed daily records of all labor, material, equipment, and subcontractor costs associated with the directed work, including time and material tickets where applicable.
- The Contractor shall notify the Owner/Architect promptly of any conditions that materially affect the scope, cost, or schedule of the directed work as it proceeds.
- The Contractor shall submit a detailed cost and schedule proposal for the directed work within the time specified below, for negotiation of a formal Change Order.
Authorization & Acknowledgment
Issued By — Owner / Architect
Acknowledged By — General Contractor/Construction Manager
Printing this often? Keep your work.
The template pack saves your entries in Word & Excel, adds your company logo, and reuses across every project — no more re-typing.
About the Construction Change Directive template
A Construction Change Directive (CCD) lets the owner or architect order a change and direct the contractor to proceed even before the parties agree on price or time. This CCD template documents the directed change and the basis for adjusting the contract, keeping work moving while the cost is negotiated.
What's included
- Directed change description
- Basis for cost adjustment (lump sum, unit price, T-and-M)
- Schedule impact and reservation of rights
- Architect/owner direction and signatures
- Reference for later change-order reconciliation
- Delivered in Word, Excel, and fillable/printable PDF
How to use it
- Describe the change the owner is directing
- State the basis for pricing the adjustment
- Direct the contractor to proceed and note schedule impact
- Reconcile to a formal change order once cost is agreed
Frequently asked questions
What is a Construction Change Directive?
A CCD is a written order from the owner or architect directing the contractor to perform a change before price and time are agreed, so the work is not delayed by negotiation.