Construction Change Directive (CCD)

Free to fill in and print in your browser. A printable, owner-directed change when agreement on cost or time has not been reached — directs work to proceed while negotiations continue. Auto-calculating cost estimate with markup. Edit inline, print clean. Need to save your data, add your logo, or reuse across projects? Get the template pack ↓

Template Pack
Construction Change Directive Pack
$25USD
  • Save data · reuse across projects
  • Add your logo & company branding
  • Works offline · no login
Word .docx Excel .xlsx PDF fillable PDF static
Get the pack
Autosaved
Pack🔒Your logo
with pack
Construction Document · CCD-01

Construction Change Directive

CCD №
Date
The Contractor is directed to proceed immediately with the work described herein.
This directive is issued without agreement on cost or time. A formal Change Order will follow upon negotiation.
§01

Project & Parties

Identify the project and the contracting parties to whom this directive applies.
§02

Basis of Directive

Why this directive is being issued without prior agreement on cost or time.
§03

Scope of Directed Work

Describe in plain language exactly what work is directed to proceed. Reference drawings and sketches where possible.
+
§04

Preliminary Cost Estimate

These amounts are preliminary estimates only — final costs subject to negotiation and formal Change Order.
Cost Category Estimated AmountNotes
Estimated Total $0
§05

Method of Determining Final Cost

Indicate how the final cost of this directed work will be established.
§06

Schedule Impact

Quantify schedule effect with justification, including critical-path or milestone references.
calendar days
§07

Contractor Obligations

Conditions the General Contractor/Construction Manager must follow upon receipt of this directive.
  1. The Contractor shall proceed with the directed work immediately upon receipt of this directive, regardless of whether agreement has been reached on cost or time.
  2. The Contractor shall maintain detailed daily records of all labor, material, equipment, and subcontractor costs associated with the directed work, including time and material tickets where applicable.
  3. The Contractor shall notify the Owner/Architect promptly of any conditions that materially affect the scope, cost, or schedule of the directed work as it proceeds.
  4. The Contractor shall submit a detailed cost and schedule proposal for the directed work within the time specified below, for negotiation of a formal Change Order.
§08

Authorization & Acknowledgment

The directing party's signature authorizes the work to proceed; the directed party's signature acknowledges receipt.

Issued By — Owner / Architect

Acknowledged By — General Contractor/Construction Manager

Printing this often? Keep your work.

The template pack saves your entries in Word & Excel, adds your company logo, and reuses across every project — no more re-typing.

Get the pack — $25
● Saved in this browser only · not synced across devices Export entries as JSON ↓
BBuildwise Consulting · projects@buildwise.construction CCD-01 · Rev 2026.05

About the Construction Change Directive template

A Construction Change Directive (CCD) lets the owner or architect order a change and direct the contractor to proceed even before the parties agree on price or time. This CCD template documents the directed change and the basis for adjusting the contract, keeping work moving while the cost is negotiated.

What's included

  • Directed change description
  • Basis for cost adjustment (lump sum, unit price, T-and-M)
  • Schedule impact and reservation of rights
  • Architect/owner direction and signatures
  • Reference for later change-order reconciliation
  • Delivered in Word, Excel, and fillable/printable PDF

How to use it

  1. Describe the change the owner is directing
  2. State the basis for pricing the adjustment
  3. Direct the contractor to proceed and note schedule impact
  4. Reconcile to a formal change order once cost is agreed

Frequently asked questions

What is a Construction Change Directive?

A CCD is a written order from the owner or architect directing the contractor to perform a change before price and time are agreed, so the work is not delayed by negotiation.